On-site construction of the social flag project, the installation of the 1st to 3rd steel structures of the office building was completed, and the steel columns of 4 or more floors were under construction.
On-site construction of the project of Zhengshangxiang Mingzhu: The fifth floor of the No. 4 building was completed. Welding five-level beams. The seven-level elevation is leveled. Eight-layer welded secondary beam. Nine layers of butt joint beams. Thirteen layers of hoisting main beams. Fifteen layers of hoisting main beams.
Building No. 5: feeding (steel beam, floor).
Building No. 6: The second floor is docked to the main beam. Five layers are docked to the main beam.
Changxing Steel Structure adheres to the original intention of the essence of the building and has been acting.